Skip to content
  • About us
    • Goals and Objectives
    • Our statement of faith
    • Previous Achievements
    • Privacy Policy
    • School Calendar
    • The Children
    • The Team
    • Vision
    • What we do
    • Where We Are
    • About Cor & Grace Koelewijn
    • Partners
  • Action
    • What may we do for you?
    • What Others Have Done
      • Corporate Donors
      • EWS
      • Fritom Group
      • Groups & Volunteers
        • Team ‘ECOstyle’ 2010 Netherlands
        • Team Roseville, California – USA
    • What YOU can do
      • Contribute To The buildings
      • Donating to Heart For Children
      • Prayer Points
      • Sponsor an orphan
      • Volunteer
  • Links
    • For Downloads
    • MultiMedia Links
    • To Contact Us
  • Language
    • Nederlands
    • Deutsch
  • Project Progress
    • 2021-KHS-Toilets
    • 2021-KHS-GirlsDorms
    • 2021-Staff-Apartments
Heart For Children – Uganda

Category: 2021 Staff Apartments

The process of constructing our new staff apartment block in 2021

2021 Staff Apartments

Tiles in Kitchen & Bathroom

By Joshua | 3 December, 20213 December, 2021 by Joshua

As the painters are still finalizing, there has been a couple of other activities taking place like; adding floor tiles while the plumbers are installing the kitchen and bathrooms.

2021 Staff Apartments

Different Activities On-Going!

By Joshua | 22 November, 202125 November, 2021 by Joshua

This week, our builders are organizing floor tiles,final painting and fixing window glasses.

2021 Staff Apartments

Staff House Progress

By Joshua | 27 October, 202127 October, 2021 by Joshua

As electrical wires have already been installed, the painter is still organizing for painting.

2021 Staff Apartments

Staff House Progress

By Joshua | 8 October, 20218 October, 2021 by Joshua

With all the tiles on,this week the builders have been fixing doors, windows and electrical installation even while prep-work for painting is taking place.

2021 Staff Apartments

Roof Tiles On Staff House

By Joshua | 30 September, 202130 September, 2021 by Joshua

Having finished the inside plastering, this week our builders have done a lot to bring up the beauty of our staff house.The next move will now target the fitting , floor finishing and painting work. We can give a credit to this.

2021 Staff Apartments

Plastering Continues…

By Joshua | 18 September, 202118 September, 2021 by Joshua

As some have been inside for plastering work, other members have been also organizing the roof by putting water proof coating to avoid leakages as we prepare before we can add the roof tiles. High ceilings and a roof made with plaster & roof tiles makes for a more comfortable temperature inside in our tropical…

2021 Staff Apartments

Plastering Begins

By Joshua | 10 September, 202110 September, 2021 by Joshua

As the roof is still drying, the builders have started on plastering!

2021 KHS Girls Dormitory 2021 Staff Apartments

This Week’s Activities

By Joshua | 31 August, 202131 August, 2021 by Joshua

Due to availability of enough labour force, many activities have been able to move on concurrent.Here we see Kidele and his team doing an extension on the material yard, as Denis and Epure busy on sewage line.Peres is busy with plumbing in the new staff house and Kissa and his team are preparing the new…

2021 Staff Apartments

New Staff House Update

By Joshua | 13 August, 202113 August, 2021 by Joshua

Having finished the roof ceiling, this week our builder Kanyama is now trying to finish the remaining sides of the walls a the roof cement is still drying and at the same time Brian our electrician doing the the wiring.

2021 Staff Apartments

Continue with Ceiling Plastering

By Joshua | 19 July, 202119 July, 2021 by Joshua

After struggling with the front side, this week the builders are on behind side.