Skip to content
  • About us
    • ANBI (Dutch Charity)
    • Goals and Objectives
    • Our statement of faith
    • Previous Achievements
    • Privacy Policy
    • School Calendar
    • The Children
    • The Team
    • Vision
    • What we do
    • Where We Are
    • About Cor & Grace Koelewijn
    • Partners
  • Action
    • What may we do for you?
    • What Others Have Done
      • Corporate Donors
      • EWS
      • Fritom Group
      • Groups & Volunteers
        • Team ‘ECOstyle’ 2010 Netherlands
        • Team Roseville, California – USA
    • What YOU can do
      • Contribute To The buildings
      • Donating to Heart For Children
      • Prayer Points
      • Sponsor an orphan
      • Volunteer
  • Links
    • For Downloads
    • MultiMedia Links
    • To Contact Us
  • Language
    • Nederlands
    • Deutsch
  • Project Progress
    • 2024-khs-girls-dormitory
    • 2025 KHS Class Block C
    • 2021-KHS-Toilets
    • 2021-Staff-Apartments
    • 2021-KHS-GirlsDorms
Heart For Children – Uganda

Recent Comments

    Recent Posts

    • Dorm Walls Completion
    • Cor & Grace 30th Wedding Anniversary
    • New Dorm, New Roof
    • KHS Boys-Dorm Walls
    • Concrete-Slab Casting BoysDorm KHS

    Archives

    Categories

    Meta

    • Log in
    • Entries feed
    • Comments feed
    • WordPress.org

    Category: 2021 Staff Apartments

    The process of constructing our new staff apartment block in 2021

    2021 Staff Apartments

    Tiles in Kitchen & Bathroom

    By Hajusu | 3 December, 20213 December, 2021 by Hajusu

    As the painters are still finalizing, there has been a couple of other activities taking place like; adding floor tiles while the plumbers are installing the kitchen and bathrooms.

    2021 Staff Apartments

    Different Activities On-Going!

    By Hajusu | 22 November, 202125 November, 2021 by Hajusu

    This week, our builders are organizing floor tiles,final painting and fixing window glasses.

    2021 Staff Apartments

    Staff House Progress

    By Hajusu | 27 October, 202127 October, 2021 by Hajusu

    As electrical wires have already been installed, the painter is still organizing for painting.

    2021 Staff Apartments

    Staff House Progress

    By Hajusu | 8 October, 20218 October, 2021 by Hajusu

    With all the tiles on,this week the builders have been fixing doors, windows and electrical installation even while prep-work for painting is taking place.

    2021 Staff Apartments

    Roof Tiles On Staff House

    By Hajusu | 30 September, 202130 September, 2021 by Hajusu

    Having finished the inside plastering, this week our builders have done a lot to bring up the beauty of our staff house.The next move will now target the fitting , floor finishing and painting work. We can give a credit to this.

    2021 Staff Apartments

    Plastering Continues…

    By Hajusu | 18 September, 202118 September, 2021 by Hajusu

    As some have been inside for plastering work, other members have been also organizing the roof by putting water proof coating to avoid leakages as we prepare before we can add the roof tiles. High ceilings and a roof made with plaster & roof tiles makes for a more comfortable temperature inside in our tropical…

    2021 Staff Apartments

    Plastering Begins

    By Hajusu | 10 September, 202110 September, 2021 by Hajusu

    As the roof is still drying, the builders have started on plastering!

    2021 KHS Girls Dormitory 2021 Staff Apartments

    This Week’s Activities

    By Hajusu | 31 August, 202131 August, 2021 by Hajusu

    Due to availability of enough labour force, many activities have been able to move on concurrent.Here we see Kidele and his team doing an extension on the material yard, as Denis and Epure busy on sewage line.Peres is busy with plumbing in the new staff house and Kissa and his team are preparing the new…

    2021 Staff Apartments

    New Staff House Update

    By Hajusu | 13 August, 202113 August, 2021 by Hajusu

    Having finished the roof ceiling, this week our builder Kanyama is now trying to finish the remaining sides of the walls a the roof cement is still drying and at the same time Brian our electrician doing the the wiring.

    2021 Staff Apartments

    Continue with Ceiling Plastering

    By Hajusu | 19 July, 202119 July, 2021 by Hajusu

    After struggling with the front side, this week the builders are on behind side.