Category: Project Progress

All stories related to project implimentation

As we have reported earlier, the preparation for roof casting on KHS-Dorm is ongoing… This week all our builders have concentrated all their effords on this project. We are now working on casting the floor that covers some four rooms… …

Dormitory Concrete Casting Read More »

The Kimbilio site engineer and his team are again back to begin on preparing for the slab work on High School dormitory. According to the Engineer and Uncle Jacob, as they were inspecting and assessing the work on ground, they …

Preparing For Roof Casting On KHS-Dormitory Read More »

Like previous years, our school has been selected to offer the trainees some good technical skills. On arrival day, our Director; Cor Koelewijn and the site Engineer Obura Besweri are communicating our expectation from them. These internees have been divided …

Internees from AURO Institute Read More »

As we are nearing the beginning of term three, a lot of preparations, staff meetings have been on going to make every thing possible. Both Kimbilio Primary and High School Staff reported a week in advance to start planning, scheming …

Welcoming Term Three-2019 Read More »

One of the heavy projects is this of putting the tiles because it is so expensive. This last bit of roof covers three classes and the wash rooms, which were remaining on the side of the primary section. We are …

Roof Tiles On Last Primary Section Read More »

As the primary school is getting to it’s final stage of phase one, we thank God for the great work which is on going on at the High School including the new dormitory block for boys.  What you need to …

Roofing Taking Place On Both Schools Read More »

Tagged with: , ,

In the same humble way we began building Kimbilio High School, we are now setting up our Kimbilio High School Dormitory. As you may be able to see, our newly recruited Site-Engineer together with his hard working team have made a …

High School Dormitory Building Read More »

As Kimbilio family, we give thanks to God for all the results of primary seven exams. Last year we had twenty candidates of which we scored seven in Div-1 and the rest passing highly in Div-2, and one pupil of …

Kimbilio HighSchool enters their newly finished building. Term-I-2019 Read More »

As you may know, Kimbilio has a guest house for all the volunteers and guests that want to come and visit or contribute to the children’s ministry here in Tororo. To reduce on the electricity bill we have embarked on …

Solar Installation On Guest House Read More »

The builders have finished casting the first half of the concrete ceiling of our new high school block. This means two classrooms are now covered.     The casting of the next two classrooms will have to wait until this …

High School Building Progress 2018Wk29 Read More »