Second Girls’ Dorm Being Set
Having finished with the wall columns, our builders are now busy bringing up the wall foundation. As you can see Kidele and the team are working so hard to have another girls’ dorm in place.
A description of the construction progress of the 2021 new Girls Dormitory.
Having finished with the wall columns, our builders are now busy bringing up the wall foundation. As you can see Kidele and the team are working so hard to have another girls’ dorm in place.
The builders have been working tirelessly to bring about the beauty of our structure.As one side of the roof is already covered, we believe by the end of the week, all will be roofed.Thanks to all who have made it a success and soon the High School Girls will be occupying.
Grateful to our builders’ speed that by Monday this week, all the trusses have been raised.This now calls for preparation of buying the roof tiles soon.
We report that work on this dorm has moved at a good speed as we finished plastering inside and this week the outside plastering will be done too. Then we remain with the plumbing, electrical and the roof work.
After all other hectic work, finally our builders are now on inside plastering and soon will begin on outside.
As metal fabricators are yet to begin on it’s roof trusses, here the builders are raising the walls for roofing preparation by adding some bricks after beam level.
This week marks the end of concrete casting that has taken three days people working tirelessly.
Having prepared all form work of 4 bedrooms and 1 bathroom, here the builders are preparing the roof for concrete casting which is now few days. The red-clay bricks are what is called here ‘maxpans’. They make the hanging floor kind of hollow with air pockets inside, thereby reducing the total weight of the floors…
Having set the formwork for 4 bedrooms, they are now left with the bathrooms only. Then the next work will be setting electrical conduits and setting the maxpans (hollow clay brickets)