Project Progress

Week 17-Roofing

The roof structure is in place.Next job will be to put the tiles on. The builders are meanwhile working on the plastering of the outside walls and our own staff are painting the classrooms inside. We hope to have it done by the time the school starts again after the easter holidays. Link: http://www.heart4children.org/en/what-we-do/project-progress.htm For…

Project Progress

Week 13 of First School- Block

All the concrete-work is finished on the 1st school-block and now we are preparing for the placement of the roof trusses that have been waiting for some time already. The builders are now working on the plastering of the classrooms. One of the classrooms is already in use by the P3 class. Link: httpc://www.heart4children.org/en/what-we-do/project-progress.htm For…

Project Progress

School-Block Wk40-2010

The work on the School Block continues… After casting all the footing of the columns, the work continues on the walls of the foundation. In the meantime the driver is working marathon as the foundation needs 140 truckloads of rock to fill… Please check out the project progress page for a panorama picture. Link: http://www.heart4children.org/en/what-we-do/project-progress.htm…