New Staff House Update
Having finished the roof ceiling, this week our builder Kanyama is now trying to finish the remaining sides of the walls a the roof cement is still drying and at the same time Brian our electrician doing the the wiring.
Having finished the roof ceiling, this week our builder Kanyama is now trying to finish the remaining sides of the walls a the roof cement is still drying and at the same time Brian our electrician doing the the wiring.
This is yet another new connection route that runs from boys dorm to the the girls’ dorm that has been covered with murram. This will in future be covered with cement pavers.
After our builders had finished the raising of walls and veranda casting, they have been on the staircases and veranda columns which soon will be done.
As the bigger projects have always taken priority first, we have not under looked the small ones, all that help in complimenting each other.Here we see Moses Opio very busy producing the road curbs and pavers that have added beauty to our Kimbilio Campus.
Apart from the main projects, we have been working on other projects like this road with it’s drainage channel and cable trench. The workers here are making a cable trench where the new electrical & network cables will be installed. Next will be the new sewage pipes. Then we will pave the road with cement…
Over the past two weeks, our painters have worked so hard to make our dinning hall shine like never before.As you can see both inside and outside are now glittering after serious paint-job!
Having finished preparation for veranda floor casting, this week we see the veranda already been cast and now we are working on the toilet walls.
After struggling with the front side, this week the builders are on behind side.
After working on roof mesh, this week our builders are busy on adding cement.Due to technicalities of this kind of roof ceiling, it might might take them some few weeks.
After the raising of the walls, the builders are now working on veranda concrete casting and also finishing up the last section of the toilets.