Plastering Outside
We report that work on this dorm has moved at a good speed as we finished plastering inside and this week the outside plastering will be done too. Then we remain with the plumbing, electrical and the roof work.
A description of the construction progress of the 2021 new Girls Dormitory.
We report that work on this dorm has moved at a good speed as we finished plastering inside and this week the outside plastering will be done too. Then we remain with the plumbing, electrical and the roof work.
After all other hectic work, finally our builders are now on inside plastering and soon will begin on outside.
As metal fabricators are yet to begin on it’s roof trusses, here the builders are raising the walls for roofing preparation by adding some bricks after beam level.
This week marks the end of concrete casting that has taken three days people working tirelessly.
Having prepared all form work of 4 bedrooms and 1 bathroom, here the builders are preparing the roof for concrete casting which is now few days. The red-clay bricks are what is called here ‘maxpans’. They make the hanging floor kind of hollow with air pockets inside, thereby reducing the total weight of the floors…
Having set the formwork for 4 bedrooms, they are now left with the bathrooms only. Then the next work will be setting electrical conduits and setting the maxpans (hollow clay brickets)
Due to availability of enough labour force, many activities have been able to move on concurrent.Here we see Kidele and his team doing an extension on the material yard, as Denis and Epure busy on sewage line.Peres is busy with plumbing in the new staff house and Kissa and his team are preparing the new…
After our builders had finished the raising of walls and veranda casting, they have been on the staircases and veranda columns which soon will be done.
Having finished preparation for veranda floor casting, this week we see the veranda already been cast and now we are working on the toilet walls.