Plastering Outside
We report that work on this dorm has moved at a good speed as we finished plastering inside and this week the outside plastering will be done too. Then we remain with the plumbing, electrical and the roof work.
We report that work on this dorm has moved at a good speed as we finished plastering inside and this week the outside plastering will be done too. Then we remain with the plumbing, electrical and the roof work.
This week, our builders are organizing floor tiles,final painting and fixing window glasses.
After all other hectic work, finally our builders are now on inside plastering and soon will begin on outside.
As electrical wires have already been installed, the painter is still organizing for painting.
As metal fabricators are yet to begin on it’s roof trusses, here the builders are raising the walls for roofing preparation by adding some bricks after beam level.
With all the tiles on,this week the builders have been fixing doors, windows and electrical installation even while prep-work for painting is taking place.
This week marks the end of concrete casting that has taken three days people working tirelessly.
After such along period of time, there was some kind of tear that needed some replacement.Now this time, we have again tried very much to add in more science as you may see to make it push for more years.I can say that indeed this is an advanced technology as compared to the first one.…
Having finished the inside plastering, this week our builders have done a lot to bring up the beauty of our staff house.The next move will now target the fitting , floor finishing and painting work. We can give a credit to this.