Ceiling Plastering
After working on roof mesh, this week our builders are busy on adding cement.Due to technicalities of this kind of roof ceiling, it might might take them some few weeks.
After working on roof mesh, this week our builders are busy on adding cement.Due to technicalities of this kind of roof ceiling, it might might take them some few weeks.
After the raising of the walls, the builders are now working on veranda concrete casting and also finishing up the last section of the toilets.
Besides the usual project development like staff house, boys’ dorm and girls’ dorm, there has been construction of the wall fence. It runs from our main gate on the left covering the children circles up to the lower gate to the guest house. We will soon reach the lower gate to the delight of our…
Due to high level of spreading of this new virus unlike the first one, this time as we had said that our teaching staff are on the ground to continue with other activities available to help them earn a living, the administrators have at least advised them to have a small break of two weeks…
Just like last time, this time when the president announced the second lock-down of all schools, our teachers immediately convened a planning meeting to begin from where they stopped last time.As we said on 7th July 2020 in our article on the website, the same teachers have been attracted NOT by choice but by circumstances…
Due to second wave of CORONA VIRUS that is again hitting our country again, the president his excellency Yoweri Museveny addressed the nation on national TV yesterday night. The major points in his communication were the closing of all the Schools, places of worship, public gathering, public transport not to cross to the neighboring Districts…
Still this week, the builders are adding more wire-mesh support in preparations for plastering the ceiling. After we create a plastered ceiling, we can waterproof it and add the times. When the roof is finally waterproof, then we can continue with finishing the plastering work on the inside. Soon… 😉
This week,the building is at beam level and both windows and door frames are already fixed.
Can you see now how the work is moving on at high speed?Here we started with inside walls and before this week is gone, we expect the start on the outside walls.
Our new staff house is being fitted with metal roof trusses. And a start is made on the fitting of wire-mash that will support the plastered ceiling. Here we see Patrick and Ezra at work