Organizing For Roof Concrete
Our builders are working hard to set the roof for concrete pouring. This is the most hardest part because if not done well, it can lead to collapsing. We believe some few weeks from now, it will be done.
All stories related to project implimentation
Our builders are working hard to set the roof for concrete pouring. This is the most hardest part because if not done well, it can lead to collapsing. We believe some few weeks from now, it will be done.
As we are still on the journey of new girls’ dorm trying to organizing for the roof concrete, again this month, we are using one stone to kill another bird. We are glad to show you what is happening with the second boys’ dormitory. Ernest and the Bobcat as usual are splitting the rock to…
The builders are now organizing the re-bars for concrete floor casting.
This week all the walls , window and door frames of new girls’ dorm have been fixed. Now the builders are casting the concrete columns.
Just a few days after floor concrete pouring, we now see the dorm coming up and by the end of next week,we shall be planning for fixing of door and window frames.With all the materials available and this man-power,work is going to move on well.
A combination of all workers making it happen by all means. A four bed roomed dorm took all these workers almost 16 hours to get it finished.The work was a bit hectic but we thank God for the strength our people had. At least now are going to begin on the walls this very week.
This Week still the builders are still pouring the concrete wall foundation.
Having finished the wall foundation building, this has been a week of ferrying marrum and filling the rooms.
Having finished with the wall columns, our builders are now busy bringing up the wall foundation. As you can see Kidele and the team are working so hard to have another girls’ dorm in place.
We are grateful that God brought the Dutch family at the right time when we had just finished putting the roof tiles on the High School toilet.For the one week they have been on ground, a lot has been achieved through their effort especially the plumbing work. Also as the team has been on toilet…